Action Taken Report (ATR) Tracking
Repair of Main Arterial Road Potholes
Deadline Passed: Oct 20, 2026 (4 days overdue)
45% Completed
Latest Remarks (Oct 23): "Work delayed due to unseasonal rain. Tender process completed, raw materials acquired. Need 3 more clear days to finish laying asphalt."
Setup Dengue Testing Camps in Ward 4 & 5
Deadline: Oct 28, 2026
60% Completed
Latest Remarks (Oct 24): "Ward 4 camp is operational. Kits dispatched for Ward 5, will be functional by tomorrow morning."
Issue Circular for Mandatory Rainwater Harvesting Certification
Deadline: Oct 25, 2026
90% Completed
Latest Remarks (Oct 22): "Draft circular prepared and vetted by legal team. Pending final signature from District Collector."